How Many Bricks Per Square Foot? Modular, Standard, Queen and King, With Mortar
Materials November 26, 2026

How Many Bricks Per Square Foot? Modular, Standard, Queen and King, With Mortar

A modular brick wall takes 6.75 bricks per square foot with a 3/8 inch mortar joint, or 675 per 100 square feet, before waste. That figure is from the Brick…

A modular brick wall takes 6.75 bricks per square foot with a 3/8 inch mortar joint, or 675 per 100 square feet, before waste. That figure is from the Brick Industry Association’s Technical Note 10, Table 4, and it assumes running bond and solid units laid in full mortar beds. Standard brick comes in at about 6.55 per square foot, queen at about 5.76, and king at about 4.61, each from the manufacturer’s own size chart. Add at least 5 percent for breakage, and 15 to 25 percent to the mortar. Below is the whole table, the mortar that goes with it, and the corrections for header courses and openings, so you can check any number a calculator gives you, including mine.

I sell websites to masonry contractors, and I build free calculators like this one to earn a look. Every number here is read from a named source with the date I read it.

Key takeaways

  • Modular brick, 3/8 inch joint: 675 bricks per 100 sq ft. With a 1/2 inch joint, 727. Both from BIA Technical Note 10, Table 4, read 2026-09-14.
  • Mortar for modular brick: 5.5 cubic feet per 100 sq ft at 3/8 inch joints, 6.9 at 1/2 inch; that is 8.1 cubic feet per 1,000 brick at 3/8 inch. Same table.
  • Waste: at least 5 percent on brick, 15 to 25 percent on mortar. BIA’s words: “as a general rule, at least 5 percent is added to the net brick quantities delivered to the jobsite” and “add 15 to 25 percent to the net mortar quantities.”
  • Manufacturer figures run slightly higher for modular. Glen-Gery’s chart lists 6.86 modular brick per square foot and 6.55 for standard (glengery.com/brick-sizes, read 2026-09-14). The gap is the joint width and the unit’s exact face size. Use the number for the brick you are actually buying.
  • Header courses change the count. Common bond with full headers every fifth course adds one fifth to the brick quantity: BIA’s example takes a standard brick wall from 655 to 786 per 100 sq ft.
  • The method is the wall-area method. Net wall area (gross area minus openings) times the quantity per square foot. It is, in BIA’s words, “the most widely used estimating procedure” because of “its simplicity and accuracy.”

How many bricks per square foot, by size

Two things set the number: the face size of the brick and the width of the mortar joint. The tables below give both the industry reference and one manufacturer’s chart, because they do not agree to the decimal, and the difference is real money on a big wall.

The industry reference: BIA Table 4 (modular sizes)

Nominal dimensions include the mortar joint. Quantities are per 100 square feet of wall, running or stack bond, no waste.

Brick Nominal W × H × L (in) Joint Brick per 100 sq ft Mortar, cu ft per 100 sq ft Mortar, cu ft per 1,000 brick
Modular 4 × 2 2/3 × 8 3/8 675 5.5 8.1
Modular 4 × 2 2/3 × 8 1/2 727 6.9 10.3
Engineer modular 4 × 3 1/5 × 8 3/8 563 4.8 8.5
Engineer modular 4 × 3 1/5 × 8 1/2 605 6.1 10.8
Closure modular 4 × 4 × 8 3/8 450 4.1 9.1
Roman 4 × 2 × 12 3/8 600 6.4 10.7
Norman 4 × 2 2/3 × 12 3/8 450 5.1 11.2
Engineer Norman 4 × 3 1/5 × 12 3/8 375 4.4 11.7
Utility 4 × 4 × 12 3/8 300 3.7 12.3

Source: Brick Industry Association, Technical Note 10, “Dimensioning and Estimating Brick Masonry,” Table 4, read 2026-09-14. Non-modular standard brick (3 5/8 × 2 1/4 × 8) at a 3/8 inch joint is 655 per 100 sq ft in BIA’s worked example.

One manufacturer’s chart: Glen-Gery

Specified dimensions, brick per square foot as the maker publishes them.

Brick Specified T × H × L (in) Brick per sq ft Mortar, cu ft per 100 sq ft
Modular 3 5/8 × 2 1/4 × 7 5/8 6.86 5.53
Standard 3 5/8 × 2 1/4 × 8 6.55 5.47
Roman 3 5/8 × 1 5/8 × 11 5/8 6.00 6.43
Queen 3 × 2 3/4 × 7 5/8 5.76 4.03
King 3 5/8 × 2 3/4 × 9 5/8 4.61 not read

Source: Glen-Gery brick sizes chart, read 2026-09-14. The chart notes that units per linear foot use nominal 3/8 inch joints and that size and weight vary by plant.

Why the two sources differ

BIA works from nominal dimensions, where a modular brick plus its joint is exactly 8 inches long and 2 2/3 inches high, so three courses make 8 inches and 675 bricks fill 100 square feet. A manufacturer’s chart works from the specified unit and its own joint assumption, so 6.86 is what that maker’s modular brick takes. Neither is wrong. If you are ordering from a specific plant, use its chart. If you are checking a bid, the BIA figure is the one everyone can point at.

The method: wall-area estimating in four steps

  1. Measure the gross wall area. Length times height, in feet, for each wall face.
  2. Subtract the openings. Doors, windows, vents. The result is net wall area.
  3. Multiply by brick per square foot. 6.75 for modular at 3/8 inch joints, or the chart figure for your brick.
  4. Add waste. At least 5 percent on brick. BIA adds that “particular job conditions or experience may warrant using a higher percentage.”

A 40 by 8 foot wall with one 3 by 5 foot window: gross 320 sq ft, minus 15, net 305 sq ft. At 6.75 per square foot that is 2,059 bricks, and with 5 percent waste, 2,162. Order 2,200.

The brick calculator does this arithmetic for any brick size and joint width you type in, and shows the mortar with it.

How much mortar per 1,000 bricks

BIA’s Table 4 gives 8.1 cubic feet of mortar per 1,000 modular bricks at 3/8 inch joints and 10.3 at 1/2 inch, before waste. The same document records the mason’s rule of thumb that “eight bags of masonry cement will lay 1000 modular brick,” and calls it “a very rough estimate” that “includes an unspecified amount of waste.” Use the table for the order and the rule of thumb for a sanity check.

Two corrections from the same source:

  • Hollow brick laid with face-shell bedding (structural work, not veneer) needs less mortar, “a percentage equal to the percentage of voids in the brick,” typically 25 to 35 percent less. Hollow brick in veneer, laid in full beds, uses about the same mortar as solid.
  • Mortar waste is 15 to 25 percent, more than brick waste, because mortar dries in the board, drops off the trowel, and gets mixed in batches that do not divide evenly.

For the material inside the mortar, BIA points to ASTM C270 and gives one more rule of thumb: a cubic foot of loose, damp sand yields about a cubic foot of mortar.

Bond patterns that change the count

Running bond and stack bond use the table as printed. Any pattern with header courses uses more brick, because a header shows its end instead of its face and covers less wall. BIA’s Table 6 gives the correction as a fraction to add:

Bond Add to brick count Add to mortar
Common bond, full headers every 5th course 1/5 1/15
Common bond, full headers every 6th course 1/6 1/18
Common bond, full headers every 7th course 1/7 1/21
English bond (headers every 2nd course) 1/2 1/6
Flemish bond (alternating headers and stretchers) 1/3 1/9

Source: BIA Technical Note 10, Table 6, read 2026-09-14. The corrections apply to brick whose length is twice its depth and 2 1/2 to 3 times its height, which covers modular and standard units.

What the calculator does not know

The quantity per square foot is the easy half. What a calculator cannot see:

  • Cuts at corners and openings. Every jamb and every corner in a pattern takes cut brick, and cut brick is where the 5 percent waste goes first.
  • Coring. Solid, cored and frogged units of the same size take the same count but not quite the same mortar.
  • Plant variation. Glen-Gery says it plainly: “size and weight may also vary by plant.” Two pallets from two plants can differ.
  • Your own crew. Waste is a number about people, not brick. If your last three jobs ran 8 percent, use 8.

Where the website fits into any of this

A calculator page like this one brings people who are pricing a wall, and a few of them are homeowners deciding whether to hire a mason. What they do next is search for one nearby. If your business does not show up in that search, the arithmetic above earned you nothing. The SEO for contractors article covers what shows up and why, and the general contractor website page shows what I build for trades that want to be found.

Not sure whether your business shows up when someone in your town searches for a bricklayer? Get a free online-presence check.

FAQ

How many bricks are in a square foot of wall?

About 6.75 modular bricks with a 3/8 inch joint, per the Brick Industry Association’s Table 4 (675 per 100 sq ft). Standard brick is about 6.55 per square foot, queen about 5.76 and king about 4.61, from Glen-Gery’s size chart. Figures read 2026-09-14.

How many bricks do I need for 100 square feet?

675 modular bricks at 3/8 inch joints, 727 at 1/2 inch, before waste. Add at least 5 percent, so order about 710 or 765. A wall with header courses needs more; common bond with headers every fifth course adds one fifth.

How much mortar for 1,000 bricks?

8.1 cubic feet at 3/8 inch joints and 10.3 at 1/2 inch for modular brick, before waste, per BIA Table 4. Add 15 to 25 percent for waste. Masons’ rule of thumb is eight bags of masonry cement per 1,000 modular brick, which BIA calls very rough.

What waste factor should I use for brick?

At least 5 percent on the brick, per BIA, and more if the job has many cuts or your crew’s history says so. Mortar waste is higher, 15 to 25 percent.

Does the mortar joint width change how many bricks I need?

Yes. Going from a 3/8 inch to a 1/2 inch joint on modular brick moves the count from 675 to 727 per 100 sq ft, because the nominal unit gets bigger. The same joint change moves mortar from 5.5 to 6.9 cubic feet per 100 sq ft.

See What Your Website Would Look Like

Request My Free Preview
Viktor Gazsi

Viktor Gazsi

Website Specialist

Updated November 26, 2026

Blog

Latest Blog Posts

How Much Does Drywall Cost? What Moves the Number, Room by Room
Materials

November 27, 2026

How Much Does Drywall Cost? What Moves the Number, Room by Room

Published guides put installed drywall at $1.50 to $3.50 per sq ft. What moves that number in a bedroom, bath, garage and basement, with sources.

Viktor Gazsi

Viktor Gazsi

Read More: How Much Does Drywall Cost? What Moves the Number, Room by Room